11 Key Projects in Dong Nai Reach 90–100% Site Handover: How to Manage Project Schedules with Site Data

2 phút đọc 3 lượt xem

What you will get from this article

  • A table of site handover rates for 11 key projects in Dong Nai, read by the portion still obstructed.
  • Why the 4% of land not yet handed over at an interchange or bridge abutment can shift the entire critical path.
  • A six-step site status set, and how to divide locations by chainage instead of commune boundaries.
  • A 5-step sequence to organize the location structure, plan drawings, site status, schedule and weekly planning.
  • The site-related commencement conditions in the Construction Law.

A roadbed package receives 96% of its site, yet the equipment crews still have to wait. The remaining 4% is scattered across several chainage sections, cutting right through the embankment fronts and box culvert locations. Every road project management board has faced this. It is why an aggregate percentage is rarely enough to manage a project schedule. This article starts from the site handover data of 11 key projects in Dong Nai. It then explains how to organize site data by location, status and schedule activity.

What do the 11 projects out of 25 in Dong Nai say about construction progress?

According to the Land Fund Development Center of Dong Nai City, of 25 key projects, 3 have received 100% of their site and 8 have reached 90% or more. These 11 projects are ready for concentrated construction. But it is the missing portion of the site that determines the completion date.

The figures published by Bao Xay dung (Construction Newspaper) on November 15, 2026 are summarized in the table below. The last column shows the portion still obstructed, which is how planning teams should get used to reading these figures.

Project Site handover rate Portion still obstructed
Expansion of the Ho Chi Minh City – Long Thanh Expressway 100% 0%
Ho Chi Minh City – Thu Dau Mot – Chon Thanh Expressway 100% 0%
Road 25B (Nhon Trach center – National Highway 51) 100% 0%
Bien Hoa – Vung Tau Expressway (additional work items) 98% 2%
Gia Nghia – Chon Thanh Expressway 96.9% 3.1%
Ring Road 4 – Ho Chi Minh City, Phase 1 96.2% 3.8%
Provincial Road DT.770B 96% 4%
City Political-Administrative Center 96% 4%
Dau Giay – Tan Phu Expressway 95.3% 4.7%
Provincial Road DT773 95% 5%
Nguyen Huu Canh Boulevard 93% 7%

Ten of the eleven projects are linear infrastructure. On this type of project, an obstruction of a few hundred square meters can hold back a work front several kilometers long, because the roadbed and drainage must be built continuously.

Why can 96% site handover still block the schedule?

Because the rate is calculated by area, while the schedule depends on location. If the remaining 4% falls at an interchange, a bridge abutment or a section with a cross culvert, the volume of work locked up is far larger than the area of that land. The critical path may shift with it.

Three common mistakes at project management boards:

  • Site clearance reports sit in a separate Excel file, while the schedule sits in Primavera P6 or Microsoft Project. There is no common key to tell which activities are waiting for the site.
  • Status is only “handed over / not handed over”, while a land parcel must go through inventory survey, compensation plan approval and payment before handover.
  • Locations are recorded by commune or ward, while construction crews work by Km+m. Every cross-check means looking up the plan drawing by hand.

Until these three points are fixed, any software will simply display the same aggregate number again.

What data layers does schedule management based on site data require?

You need three layers connected by one common key, location: a location tree by chainage or zone, a site status set with forecast dates, and schedule activities attached to those exact locations. Without any one layer, the data falls back into disconnected reports.

A location tree by chainage, not by administrative boundaries

For linear projects, level 1 is the work package, level 2 is the chainage section (for example Km12+000 – Km13+500), and level 3 is a specific element such as an interchange, bridge or culvert. For a facility such as an administrative center, level 2 is the zone. Commune and ward names are kept as attributes, not as the framework.

A multi-step site status set

A practical status set includes: Not surveyed, Inventory surveyed, Compensation plan approved, Compensation paid, Obstructed (complaints, resettlement, utility relocation), Handed over. Each section also carries area, number of households, forecast handover date and responsible unit. “Obstructed” should be kept separate because this group requires action from senior management.

Schedule activities attached to locations

Every activity in the master schedule (embankment of section A, construction of abutment M1…) must reference a location. Then the question “how many activities next week start on land not yet handed over” is answered with a filter, not a meeting.

Setup: steps and limitations

The sequence OneCAD typically recommends for infrastructure project management boards:

Step Area of work What to do
1 Location structure Build the location breakdown structure by work package and chainage.
2 Plan drawings Use PDF plan drawings so the team works from a shared base organized by section.
3 Site status tracking Define the site status steps and the information to track for each site section.
4 Schedule Make sure each activity in the schedule carries a location code.
5 Field issues and weekly planning Log obstructions on site and plan work week by week.

In step 1, when adding only one work package, add it under that package’s own branch. In step 2, organizing drawings and site information by location means “obstructed at which Km” reports need less manual entry.

Plan drawings for step 2 should show a chainage grid, so the planning team and the site clearance team work from the same base. If the project already has an alignment model in Civil 3D, it is a convenient source for these drawings.

Project schedule displayed as a Gantt chart. Image: Autodesk

How is the schedule updated when site handover is late?

Project members flag the affected activities to the schedule manager, for example “delay Km14 embankment by two weeks due to unpaid compensation”. The schedule manager reviews each request. If it is accepted, the scheduler revises the schedule in the scheduling software and issues the new version. Comparing it with the previous version shows which activities have shifted.

Limitations to know before deployment

Logic links and critical path recalculation are still done in dedicated scheduling software such as P6 or Microsoft Project. Tracking site sections by status is a configuration choice, not a built-in land acquisition feature, and should be set up by the project administrator. This setup also does not replace cadastral records or compensation management software. The data still needs a focal person to update it regularly.

If your organization manages multiple linear work packages and wants to trial a location and site status structure on real data, OneCAD’s Digital Construction team can work with you on a pilot project. You can request a consultation to get started.

Application in Vietnam

The Construction Law continues to require that a project at commencement has a construction site available for handover in full or in part (summary by Thu vien Phap luat). The words “in part” require the owner to prove which sections are eligible and from what date, instead of a single overall rate.

Vietnam’s national roadmap for BIM adoption steers large public investment projects toward digital data management. Location-based site tracking is the easiest place to start because no 3D model is needed: existing PDF plan drawings and P6 schedules are enough.

This approach works best for expressways, ring roads and provincial roads that receive land in phases. It also fits industrial parks with phased land allocation, and public works that depend on utility relocation.

Project management boards usually have one site clearance officer working with many communes. This person should be responsible for maintaining locations and updating statuses directly during meetings with local authorities. On site, 360-degree photos from a 360-degree site monitoring solution help confirm that a section is actually clear. This avoids cases where the handover record is signed but structures have not yet been demolished.

Where to start managing infrastructure schedules by site handover?

Start with one work package that has obstructions; do not roll out to the whole project at once. Build the location tree by chainage, assign the six-step status set, attach the current P6 schedule, run it for four weeks, then compare it with the old Excel report.

For choosing a subscription, the article comparing editions helps you match the tools you need to the scope of each edition.

Three things you can do this week: change the location column in the site clearance report to chainage, separate “Obstructed” from “Not handed over”, and attach a location code to every activity in the master schedule. Then the 96% figure shows what it really is: a list of locations with forecast dates. Is your project tracking the site by commune, by parcel or by chainage, and where is your biggest bottleneck?

Frequently asked questions

Can this setup replace Primavera P6 or Microsoft Project?

No. Logic links and the critical path are still calculated in the original scheduling software.

Can site handover be tracked without a BIM model?

Yes. The location tree can be built without a model, and PDF plan drawings serve as a shared base for each section. A Civil 3D or Revit model makes it more visual but is not required in the initial phase.

How should sensitive compensation data be handled?

Households’ personal information should stay in the compensation unit’s system. Site tracking only needs the status, area and forecast date for each section.

References

  1. Dong Nai: 11 key projects reach 90-100% site handover — Bao Xay dung, 2026-11-15
  2. Conditions for commencing construction — Thu vien Phap luat
  3. About Schedule and Workplan — Autodesk Help
  4. Import a Schedule — Autodesk Help
  5. Add, Import and Export Locations — Autodesk Help
  6. Link Sheets to Locations — Autodesk Help
  7. Configure Custom Fields and Status Sets — Autodesk Help
  8. Have You Tried?: Schedule Suggestions in Autodesk Build — Autodesk Digital Builder Blog, 2022-08-08
Cám ơn bạn đã quan tâm đến các nội dung của chúng tôi.
Để nhận ngay thông báo khi có tin tức mới từ OneCAD Vietnam, bạn có thể đăng ký nhận bảng tin thông qua email.

Đăng ký nhận bản tin

OneCadVN

Đăng ký nhận bản tin

    Mảng quan tâm

    Sau khi gửi, hãy kiểm tra hộp thư và xác nhận đăng ký. Bạn có thể hủy đăng ký bất cứ lúc nào.

    Đọc tiếp cùng chủ đề

    OneCadVN

    Xin chào quý khách

    Vui lòng để lại thông tin cần hỗ trợ, OneCadVN sẽ liên hệ lại với bạn trong thời gian sớm nhất

      (*) Thông tin bắt buộc

      Liên hệ nhanh