Dong Nai Has 11 Key Projects with 90–100% Site Handover: How to Manage Project Schedules Using Site Data

8 min read 15 views

What will you get from this article?

  • A table of site handover rates for 11 key projects in Dong Nai, read by the outstanding portion.
  • Why the 4% of land not yet handed over at an interchange or bridge abutment can shift the entire critical path.
  • A six-step site status set, and how to divide locations by chainage instead of commune boundaries.
  • A 5-step sequence for setting up Locations, Sheets, Status Sets, Schedule and Workplan in Forma Build.
  • The site-related conditions for construction commencement under the 2025 Construction Law, and the limits of the Schedule tool.

The roadbed package has received 96% of the site, yet the equipment crews are still waiting: the remaining 4% is scattered across a few chainage sections, cutting right across the embankment fronts and box culvert locations. Every road project management unit has faced this, and it is why an aggregate percentage is rarely enough to manage a project schedule. This article starts from the site handover data of 11 key projects in Dong Nai, then explains how to organize site data by location, status and schedule activity in Forma Build.

What does the figure of 11 out of 25 projects in Dong Nai say about construction progress?

According to the Dong Nai City Land Fund Development Center, of 25 key projects, 3 have handed over 100% of the site and 8 have reached 90% or more. These 11 projects are ready for construction to be ramped up, but it is the missing portion of the site that decides the completion date.

The data, published by Construction Newspaper (Báo Xây dựng), is summarized in the table below. The last column shows the outstanding portion, which is the view planning teams should get used to.

Project Site handover rate Outstanding portion
Ho Chi Minh City – Long Thanh Expressway expansion 100% 0%
Ho Chi Minh City – Thu Dau Mot – Chon Thanh Expressway 100% 0%
Road 25B (Nhon Trach center – National Highway 51) 100% 0%
Bien Hoa – Vung Tau Expressway (additional work items) 98% 2%
Gia Nghia – Chon Thanh Expressway 96.9% 3.1%
Ring Road 4 – Ho Chi Minh City, Phase 1 96.2% 3.8%
Provincial Road DT.770B 96% 4%
City Political and Administrative Center 96% 4%
Dau Giay – Tan Phu Expressway 95.3% 4.7%
Provincial Road DT773 95% 5%
Nguyen Huu Canh Boulevard 93% 7%

Ten of the eleven projects are linear infrastructure works. For this type, a single obstruction of a few hundred square meters can hold up an entire work front several kilometers long, because the roadbed and drainage must be built continuously.

Why can 96% site handover still block the schedule?

Because the rate is calculated by area, while the schedule depends on location. If the remaining 4% falls at an interchange, a bridge abutment or a section with a cross culvert, the volume of work locked up is far larger than the area of that land, and the critical path may shift accordingly.

Three common mistakes made by project management units:

  • Site clearance reports sit in separate Excel files, while the schedule lives in Primavera P6 or Microsoft Project, with no common key to show which activities are waiting for the site.
  • The status is only “handed over / not handed over”, while a land plot must go through inventory survey, compensation plan approval and payment before it is handed over.
  • Locations are recorded by commune and ward, while construction teams work by Km+m, so every cross-check requires looking up the plan view by hand.

Until these three points are fixed, any software will only redisplay the same aggregate figure.

What data layers are needed to manage a project schedule using site handover data?

You need three layers linked by one common key, which is location: a location tree by chainage or zone, a site status set with expected dates, and schedule activities tied to those exact locations. If any layer is missing, the data falls back into disconnected reports.

A location tree by chainage, not by administrative boundaries

For linear projects, level 1 is the contract package, level 2 is the chainage section (for example Km12+000 – Km13+500), and level 3 is a specific work item such as an interchange, bridge or culvert. For a facility such as an administrative center, level 2 is the zone. Commune and ward names are kept as attributes, not as the framework.

A multi-step site status set

A practical status set includes: Not surveyed, Surveyed, Compensation plan approved, Paid, Blocked (complaints, resettlement, utility relocation), and Handed over. Each section also carries its area, number of households, expected handover date and responsible unit. “Blocked” should be kept separate, because this is the group that needs management to resolve.

Schedule activities tied to locations

Every activity in the master schedule (embankment of section A, construction of abutment M1, etc.) must reference a location. Then the question “how many activities start next week on land not yet handed over” is answered with a filter, not a meeting.

Setting up in Forma Build: steps and limitations

Forma Build provides tools that can support all three layers. The sequence OneCAD typically recommends for infrastructure project management units:

Step Tool in Forma Build What to do
1 Locations Build the location breakdown structure by contract package and chainage using a spreadsheet template file.
2 Sheets + Locations Upload PDF plan views to Sheets, link them to locations, and outline each section on the drawing.
3 Status sets and custom fields Create a color-coded site status set and use it, together with custom fields, to track each site section.
4 Schedule Import the schedule from your scheduling software.
5 Issues + Workplan Log obstructions on site, plan weekly work, and track how much of the weekly plan is completed.

In step 1, import carefully: check where the imported data will be placed so the existing location tree is not affected; when adding only one contract package, add it under that package’s branch. In step 2, linking sheets to locations makes it easier to tie issues logged on site to the right section, so “which Km is blocked” reports no longer rely on manual typing.

Plan views for step 2 should be exported from the corridor model in Civil 3D with a chainage grid, so the planning team and the site clearance team work from the same base. Weekly planning and plan completion tracking in step 5 are covered in detail by OneCAD in the article Workplan features in Forma Build.

Schedule tool interface showing a Gantt chart
The Schedule tool displays the schedule as a Gantt chart. Image: Autodesk

When site handover is delayed, how is the schedule updated?

When a section is delayed, for example embankment at Km14 pending compensation payment, the scheduler revises the schedule in P6 and imports the new version.

Limitations to know before deployment

The Schedule tool is for viewing and sharing, not scheduling software: logic links and critical path recalculation are still done in P6 or Microsoft Project. Check the file formats and versions Autodesk currently supports before importing. Using status sets and custom fields to track site sections is a configuration choice and should be set up by project administrators. Forma Build also does not replace cadastral records or compensation management software; the data still needs a focal person to update it regularly.

If your organization manages multiple linear contract packages and wants to trial a location and site status structure on real data, the OneCAD Digital Construction team can work with you on a pilot project; you can request a consultation and a Forma Build quote to get started.

Application in Vietnam

The 2025 Construction Law continues to require that a project have a construction site available for full or phased handover before commencement (summary by Thu Vien Phap Luat). The word “phased” requires the owner to demonstrate which sections are eligible and from what date, rather than a single overall percentage.

The Government’s roadmap for BIM adoption steers large-scale public investment projects toward digital data management. Location-based site tracking is the easiest place to start because no 3D model is needed: existing PDF plan views and P6 schedules are enough.

This approach fits best with expressways, ring roads and provincial roads that receive the site in batches, followed by industrial parks with phased land allocation and public works that depend on utility relocation.

Project management units usually have one site clearance officer working with several communes; this person should be given permission to manage locations and update statuses during meetings with local authorities. On site, 360-degree photos from the 360 camera and AI site monitoring solution help confirm that a section is actually clear, avoiding cases where the handover record has been signed but structures have not yet been demolished.

Where to start managing infrastructure project schedules by site handover?

Start with one contract package that currently has obstructions, rather than rolling out across the entire project at once. Build the location tree by chainage, assign the six-step status set, import the current P6 schedule, run it for four weeks, then compare it with the old Excel report.

For choosing a plan, the article comparing Forma Build editions helps you match the tools you need with the scope of each edition.

Three things you can do this week: change the location column in the site clearance report to chainage, separate “Blocked” from “Not handed over”, and attach a location code to each activity in the master schedule. Then the 96% figure shows its true nature: a list of locations with expected dates. Is your project tracking site handover by commune, by land plot or by chainage, and where is your biggest bottleneck?

Frequently asked questions

Can Forma Build replace Primavera P6 or Microsoft Project?

No. The Schedule tool imports schedule files from your scheduling software to view them as a Gantt chart and share them. Logic links and the critical path are still calculated in the original scheduling software.

Can site handover be tracked in Forma Build without a BIM model?

Yes. The location tree is imported via a spreadsheet template, and PDF plan views are uploaded to Sheets to outline each section. A Civil 3D or Revit model makes things more visual but is not required in the initial phase.

How are permissions handled in Forma Build for sensitive compensation data?

Access to project tools can be managed per member, configuration should be kept with project administrators, and location management can be limited to designated people. Personal information of affected households should stay in the compensation unit’s system; Forma Build only needs the status, area and expected date for each section.

References

  1. Dong Nai: 11 key projects reach 90-100% site handover — Construction Newspaper (Báo Xây dựng)
  2. Conditions for commencing construction works under the 2025 Construction Law — Thu Vien Phap Luat
  3. About Schedule and Workplan — Autodesk Help
  4. Import a Schedule — Autodesk Help
  5. Add, Import and Export Locations — Autodesk Help
  6. Link Sheets to Locations — Autodesk Help
  7. Configure Custom Fields and Status Sets — Autodesk Help
Thank you for your interest in our content.
Subscribe by email to receive the latest news from OneCAD Vietnam.

Subscribe to our newsletter

OneCadVN

Subscribe to our newsletter

    Areas of interest

    After submitting, check your inbox and confirm your subscription. You can unsubscribe at any time.

    Keep reading

    OneCadVN

    Hello

    Please leave the information you need support with, OneCadVN will contact you in the shortest time

      (*) Required fields

      Quick contact